Collins Dauda, four others, and the $200m Saglemi Housing Project

Collins Dauda

Alhaji Collins Dauda, a former Minister of Works and Housing, together with four others have been charged for wilfully causing financial loss to the State in the $200 million Saglemi Housing Project.

Alhaji Dauda is additionally charged for intentionally misapplying public property.

He, Dauda, together with Kwaku Agyeman-Mensah, Alhaji Ziblim Yakubu, Andrew Clocanas and Nouvi Tetteh Angelo, are also facing the charge of issuing a false certificate.

Clocanas and Tetteh have been additionally and jointly charged for dishonestly causing financial loss to the State.

All the five accused persons are expected to appear before the High Court to answer the various charges.

The facts of the case are that, Alhaji Dauda, a Member of Parliament, was a Minister of the Ministry of Water Resources, Works and Housing (MWRWH) from February 2013 to March 2015, whilst Agyeman-Mensah was also a Minister of the MWRWH from April 2015 to January 2017.

Alhaji Yakubu was the Chief Director of MWRWH from July 2009 to April 2017, with Clocanas being the Executive Chairman of Construtora OAS Ghana Limited and Tetteh, a director and majority shareholder of Ridge Management Solutions DWC-LLC as well as director of VHM Ghana Limited.

In August 2012, former President John Dramani Mahama, granted executive approval to the Ministry for the construction of 5,000 affordable housing units (the Saglemi Affordable Housing Project) for sale to workers through mortgage arrangements provided by Ghana Home Loans to be implemented by Construtora OAS Limited.

The project was to be funded by a Buyer’s Credit of $200 million provided by Messrs Credit Suisse International (Credit Suisse).

On October 31, 2012, Parliament granted approval for the government to secure a facility of $200 million from Credit Suisse for the project, following a joint memorandum to Parliament by the then Minister for MWRWH, Mr Enoch Teye Mensah and the then Minister for Finance and Economic Planning, Dr. Kwabena Duffour.

On January 4, 2013, a Facility Agreement was signed between the Ministry of Finance, as borrower, and Credit Suisse, as creditor, for a facility of $200 million for the project and same day, MWRWH through the then Minister, Mr E.T Mensah, signed an Engineering, Procurement and Construction (EPC) Agreement with Construtora OAS Ghana Ltd represented by 4th accused for the construction of affordable housing units at Saglemi in the Greater-Accra Region.

The project, which was to be executed in four phases on 2,172 acres of land was at a contract price of $200 million, including consultancy services, an Escrow Management Agreement, a condition precedent to the release of the facility to the borrower, was also signed pursuant to the Facility Agreement and the EPC Agreement, between the Ministry of Finance (Borrower), the MWRWH(Account holder), the Bank of Ghana(Account holding bank) and Construtora OAS (Contractor)].

The purpose of the agreement was to ensure that the $200 million facility would be properly applied towards the development of the 5,000 housing units.

The agreement, therefore, required payments under the contract to be effected only when specific works had been duly executed, verified and certified by the consultants of the project, the Architectural and Engineering Services Limited (AESL).

The EPC Agreement provided for an advance payment of 40 per cent of the contract price to the contractor within five working days of the receipt of the facility in the Escrow Account, where the advance payment was to be applied towards specific works set out in the contract.

The remaining amount of the contract price was to be paid to the contractor based on the fulfilment of specific project milestones and the contractor was required under the agreement to set out the details of the achieved project milestones, which had to be verified and certified by the consultants before payment is done.

On January 9, 2013, Credit Suisse disbursed an amount of $198,450,000, representing the $200 million less fees and transaction expenses into the Escrow Account and on February 27, 2013, an amount of $80 million representing 40 per cent of the contract sum was transferred to Construtora OAS as advanced payment.

However, the contractor allegedly failed to apply the amount towards the purpose for, which the payment was made, thus, on February 27, 2014, Alhaji Dauda who had assumed office as the new Minister, without any parliamentary approval, allegedly reviewed the original EPC and signed the first and restated agreement with Construtora OAS, represented by its Executive Chairman, the 4th accused, and in the process, changed the scope of works and the application of the $200 million approved by Parliament for the construction of 5000 housing units.

The  new agreement required the contractor to execute the project in three phases over a site of 1,272 acres whilst the $200 million was now to be applied towards the execution of only the first phase of the project comprising just about 1,502 housing units, contrary to the executive and parliamentary approvals as well as the Facility and Escrow Management Agreements.

As a result, on April 15, 2013, the AESL signed a contract with Vito Hugo-CoordenacaGestao De Projectos (VHM) subcontracting its consultancy services under the EPC agreement to the company for $500,000,000 over a period of 24months.

This was the amount provided under the EPC Agreement for consultancy services for the 5000 housing units.

Under the agreement between AESL and VHM, a maximum amount of $2,000,000 was to be paid to AESL as not more than $2,987,750 was to be paid to VHM for their services.

This contract also provided for 40 per cent advanced payment.

In April 2015, when AESL and the VHM were still providing consultancy services under the contract, the MWRWH, allegedly entered into another contract for consultancy services with Ridge Management Solutions DWC-LLC (RMS), represented by its director and majority shareholder, Tettey, for three months at a contract sum of $5.6 million.

This was at a time RMS allegedly was not registered in Ghana as a company.

Once again, the MWRWH was required to make an advance payment of 40 per cent of the contract sum.

This contract was said to be completely outside the EPC Agreement.

Investigations revealed that Tettey, who is the majority shareholder of RMS is also a Director of VHM Ghana Limited, allegedly.

In August 2016, the 2nd accused entered into yet another consultancy agreement with RMS, this time, for what was referred to as “marketing implementation services” for a sum of $2,502,198.00 and again, the Ministry was required to make an advanced payment of 40 per cent of the contract sum, when all that while, AESL and VHM were purportedly performing the same consultancy services for the project, their consultancy agreements having been extended at various times by Mensah and Alhaji Yakubu.

On December 21, 2016, Alhaji Yakubu without recourse to Parliament allegedly reviewed the First and Restated Agreement and signed the Second and Restated Agreement, which led to a further reduction in the scope of works to 1,412 housing units at a revised contract price of $181,018,000.00 and extended the completion period of the contract to July 31, 2017 without any basis.

Between March 2014 and January 2015, an amount of $46,131,153.41 was paid to the contractor, Construtora OAS, whilst a total of $3,386,916.08 was paid to AESL and VHM when no works had been duly executed by the contractor, with the payments allegedly authorised and approved by Alhaji Dauda and Alhaji Yakubu without any evidence of specific project milestones achieved by the contractor as required under the EPC Agreement.

It is also argued that there was no justification for the advanced payment of $80 million earlier made, but between June 2015 and January 2017, a further amount of $54,066,768.16 was paid to the contractor of the project when no works had been duly executed.

Again, though there were no milestone reports supporting the payments, Mensah and Alhaji Yakubu allegedly ordered for further payments to be made to the three consultants; AESL, VHM and RMS, far in excess of the $5,000,000 stated as consultancy fees in the original EPC Agreement without any evidence of work they had done.

There were no verification and certification of actual work done by the contractor as required under the EPC Agreement though a total amount of $196,428,891.66 has been spent on the Saglemi Affordable Housing Project, with the contractor having been paid $179,904,757.78, allegedly.

Investigations revealed that the cost of works executed on the site, including consultancy services, is about $64,982,900.77.

Only 651.75 acres of land out of the 2,172 acres of land made available by the MWRWH to the contractor for the project has been developed.

Investigations further revealed that only 668 housing units were completed by the contractor.

The houses are, however, not habitable so not a single house under the project has been sold and the facility remains unpaid, resulting in huge financial loss to the Republic of Ghana.

Source: GNA

Leave A Reply

Your email address will not be published.

Shares